The Santa Clara HCP/NCCP is being developed and completed between 2005 and 2010 through a collaborative process with the Local Partners, Wildlife Agencies, stakeholders, and other interested parties. The project schedule decision chart provides an overview of the HCP/NCCP timeline.
|
Milestone
|
Estimated Completion Date
|
|
Assemble baseline data:
- Determine covered species and activities
- Develop land cover and land use maps
- Document existing conditions
- Prepare species and natural community profiles
|
2006-2007
|
|
Draft Conservation Strategy
|
2008
|
|
Completion of Draft HCP/NCCP and Draft Environmental Review documents
|
2009
|
|
Public Review/Comment Period for Draft HCP/NCCP and Draft Environmental Review documents
|
30-90 days (TBD)
|
|
Certification of the Environmental Review and Completion of Final HCP/NCCP
|
2010
|